19 October, 2018

A comprehensive testing of a combined cycle power unit No. 2 has been successfully completed at Pregolskaya TPP in Kaliningrad region

According to the test results, the combined cycle plant has confirmed the ability to carry the maximum load.

On September 9, according to the Customer's certificate of equipment acceptance after comprehensive testing, the CCGT unit No. 1 was put into operation ahead of schedule.